System improvements, upgrades and projects

We are continuously working to maintain and improve the water system.  Some of the major projects we are currently working on involve the installation of new, or the replacement of existing, equipment and facilities needed to provide safe, reliable water service.

Infrastructure Projects

Main Replacement in Monroe, CT: Osborne Lane, Ripton Ridge & Goodhill Lane

We will be replacing 4900 feet of main beginning March 28th, 2024. Work is expected to be completed by July 2024.

Main Replacement in Mystic, CT: New London Road

We will be replacing 1500 feet of main beginning in March 2024 on New London Road. Work is expected to be completed by June 2024.

Main Replacement in Stamford, CT: Ocean Drive West, Saddle Rock Road and Rogers Road

We will be replacing 4800 feet of main beginning in March 2024 in Stamford. Work is expected to be completed by end of September 2024.

Main Replacement in Westport, CT: Duck Pond Road and Saugatuck Avenue

We will be replacing 6800 feet of main beginning in February 2024. Work will start on Duck Pond Road and will continue onto Saugatuck Avenue working towards Ferry Lane. Due to construction, customers should expect minor traffic delays and possible detours during the working hours of 7:00 a.m. to 5:00 p.m. Work is expected to be completed by the end of October. Final paving will then be scheduled in coordination with the Town of Westport and CT DOT.

Main Replacement in Bridgeport, CT: Kossuth St, Maple Ave, and Jane St.

We will be replacing 3000 feet of main on Kossuth Street, Maple Ave, and Jane Street, beginning in February 2024. Due to construction, customers should expect minor traffic delays and possible detours during the working hours of 7:00 a.m. to 5:00 p.m. Work is expected to be completed by the end of May 2024. Final paving will be scheduled in coordination with the town and state.

Main Replacement in Norfolk, CT: Greenwoods Road West

We will be replacing 4100 feet of main in January 2024. Work is expected to be completed by the end of March.

Main Replacement in Seymour, CT: George Street, Martha Street, School Street & Shelton Street

We will be installing 2,500 feet of main beginning in May 2023. Work is expected to be completed by July 2023. Final paving will be scheduled in coordination with the Town of Seymour, CT.

Main Replacement in Simsbury, CT: Hoskins Road, Firetown Road, Clifdon Drive, Short Lane, Tower Drive, Scarborough Road and Katherine Lane

We will be replacing 8,766 feet of main beginning on July 10, 2023. Work is expected to be completed by the end of fall 2023. Final paving will be scheduled in coordination with the Town of Simsbury, CT.

Anderson Road and West Brother Drive Main Replacement - Greenwich

A water main replacement project is scheduled to begin on May 24, 2021 on Anderson Road and West Brother Drive, from Woodside Drive to Mallard Drive.

Main Replacement in Ridgefield, CT: Oscaleta Road

We will be replacing 4,570 feet of main beginning in May 2023. Work is expected to be completed by the end of July 2023. Final paving will be scheduled in coordination with the Town of Ridgefield, CT.

Main Replacement in Stamford, CT: Canal Street

We will be replacing 2400 feet of main on Canal Street between Jefferson Street and Ludlow Street beginning in November 2023. Due to construction, customers should expect minor traffic delays and possible detours during the working hours of 7:00 a.m. to 5:00 p.m. Work is expected to be completed by the end of 2023. Final paving will be scheduled in coordination with the town.

Main Replacement in North Canaan, CT: Lower Road and Patty Lane

We will be replacing 5,120 feet of main beginning in May 2023. Work is expected to be completed by the end of July 2023. Final paving will be scheduled in coordination with the Town of North Canaan, CT.

Main Replacement in Fairfield, CT: Rowland Road, Penfield Road, Quincy Street & Fern Street

We will be replacing 11,300 feet of main beginning in April 2023. Work is expected to be completed by the end of October 2023.

Main Replacement in Greenwich, CT: Oval Avenue & Summit Road

We will be replacing 4,800 feet of main beginning in April 2023. Work is expected to be completed by October 2023. Final paving will be scheduled in coordination with the Town of Greenwich, CT.

Main Replacement in New Milford, CT: New St, Violet Hill Ln, Second Hill Rd, Mountain View, Malletts Ln, and Hillside Ave

We will be replacing 6,620 feet of main beginning 9/25/2023. Work is expected to be completed by the end of 2023.

Pump Station Replacement in Monroe, CT: Pastors Walk Road

We will be replacing the existing pump station with a new facility on the same parcel of land beginning in May 2023. Work is expected to be completed by the end of 2023.

Main Replacement in Beacon Falls, CT: Feldspar Ave, Avenue B, Avenue C, Avenue E & Avenue E Extension

We will be replacing 3,900 feet of main beginning in May 2023. Work is expected to be completed by the end of summer 2023.

Main Replacement in Darien, CT: Park Lane, Holmes Avenue, Bayberry Drive, Sunset Road

We will be replacing 3,800 feet of main beginning in May 2023. Work is expected to be completed by the end of summer 2023.